Dec. 2025 Construction Update
WF Redevelopment
Light pole base installations and electrical underground installations are complete. Asphalt paving for the home parking lot, field house west entrance, and south bus barn entrance is finished. Parking lot striping is complete, and visitor side ramps and stairs installations are also complete.
High School
Subgrade cutting and cul-de-sac grading are currently in progress. Saw-cutting and removal of welding shop concrete have been completed.
Bleachers
Tennis court asphalt work is complete.
Elementary and High School Demolition
Demolition of the existing elementary school canopy is complete. Additionally, demolition of the existing sidewalks at both the high school and elementary school is complete.