Feb. 2025 Construction Update
As of February 2025, significant progress has been made across multiple areas of the project. The concrete pours for the baseball field are complete, while the softball field has finished concrete form setting. Turf installation is currently underway on the baseball field, and drainage fill installation is in progress for the softball field. At Walton Field, both track and bleacher demolition have been completed. Additionally, roof membrane installations are finished, and trim installation is nearing completion.