Nov. 2025 Construction Update
The Walton Field redevelopment continues to progress, with light pole bases and electrical underground installations completed, along with asphalt paving for the home parking lot, the south bus barn entrance, and the west entrance of the field house. Parking lot striping, as well as the installation of visitor-side ramps and stairs, is currently underway. Tennis court asphalt work is complete. Demolition is complete at the elementary school canopy, and sidewalks have been removed, and the high school sidewalk demolition is finished. Erosion control installations have also been completed.